On September 14,BaiChunli who is vice-president of CAS listen to a report by CuiXiangqun who is director of NIAOT and general engineer of LAMOST on recent progress of LAMOST。
Recent progress of LAMOST :
1):fabrication of submirrors will be completed before the end of this year
2):truss of MA have been smoothly installed
3):telescope will enter into stage for joint adjustment of mechanism-electronics
4):supporting system for seventy hexagonal submirrors with 1.1m in diagonal have entered into stage of overall fabrication,installing and adjusting。
5): position system of 4000 optical fibre on focal plane have started to be fabricated while small focal plane with 250 optical fibre has completed fabrication for checking and accepting
6): first prototype of spectrograph has started to be installed and adjusted。
7): dome and building will be completed before long
8): Co-focus image produced by three hexagonal submirrors with 1.1M in diagonal for spherical mirror(MB) can concentrate 80% encircled energy within circle with diameter of 0.42(best than requirement of LAMOST)。Accuracy of co-focus is from 0.1 to 0.2 arcseconds(best than requirement of LAMOST)。
after then BaiChunli inspected pre-segmenting of submirrors lab,force-actuator lab,spectrograph lab and mirror lab。
|